Panoramic produces first concentrate at Savannah

Panoramic

The Savannah nickel mine. Image: Barminco

Panoramic Resources has arrived with its first nickel-copper-cobalt at the Savannah nickel project in Western Australia, as the company targets first concentrate shipment in December 2021.

It comes as Panoramic’s circa one-million-tonne-per-annum processing plant was commissioned three weeks ahead of schedule, with tailings processing and crushing, milling and flotation circuits achieving operational stability.

Primero’s processing team is now fully mobilised to site following the completion of requisite preparatory works.

Panoramic aims to commence concentrate haulage from site to Wyndham Port next week, to be completed by haulage contractor Cambridge Gulf (CGL) which has already recruited a local workforce for the task.

Panoramic managing director and chief executive officer Victor Rajasooriar said first concentrate is validation for his company’s diligence at Savannah.

“It’s fantastic to see the careful planning and hard work undertaken over the past 12 months culminate in the commencement of processing ahead of schedule,” he said.

“The leadership group at site and our business partner Primero have been working hard to deliver on the restart of the processing plant and have achieved this safely.

“We have been pleased with the performance of the plant through the commissioning phase and will now target ramp up to steady state production over the coming months.” 

Rajasooriar said Savannah’s ramp up comes at just the right time, with prices faring well. 

“As underground mining continues at Savannah and ore production steadily builds, the surface ore stockpile, which is currently sitting at over 120,000 tonnes, will provide consistent feed to the processing plant and reduce any risk to throughput rates,” he continued.

“The timing of first concentrate production has also aligned well with prices for nickel, copper and cobalt, which have continued to show strength as the year progresses.”

Panoramic awarded CGL a three-year concentrate haulage contract at Savannah in September, and offered indications the project was tracking well as Barminco carried out initial underground mining to expectations.

To keep up to date with Australian Mining, subscribe to our free email newsletters delivered straight to your inbox. Click here.