Doray Minerals has begun underground development at Deflector, following its first concentrate shipment.

The miner’s first shipment of gold copper concentrate, totalling 500 dry tonnes, was dispatched from the site earlier this month, only 14 months after taking over the operation from Mutiny Gold.

On the back of this development, Doray has also begun underground access, following the progression of the open pit and firing of the portal.

Ore from underground development and eventual stoping will be stockpiled whilst production comes from treating open pit ore over the next eight to nine months.